Pineland Engineering prepares permit-ready construction documents for North Bay Village, Miami-Dade County, Florida projects and coordinates directly with the North Bay Village Building Department during plan review — so you get your permit faster.

Quick Answer

Email permit applications as PDFs to [email protected]. For help with a filing, call the Building Department at (305) 754-6740, Monday through Friday, 8:00 am to 4:00 pm. The Village’s Online Services menu lists Apply for Permits, which opens the Building Department’s forms and email instructions.

The North Bay Village Building and Zoning Department handles permits on Harbor, North Bay and Treasure islands. Its office is at 1666 Kennedy Causeway, Suite 101, North Bay Village, FL 33141. For a property across the causeway in Miami or Miami Beach, start with that city’s building office. Miami-Dade’s Government Boundaries Map can help identify the municipality before an applicant chooses a form.

Where Can I Verify the Official Requirements?

What goes in the email to the Building Clerk?

Start with the North Bay Village Permit Application and the separate Permit Package Requirements checklist.

On the application, enter the job address and tax folio, select the permit type and describe the work. Use the value, linear feet and square feet fields that apply to the job. For a project involving several trades, the Village asks for all trade applications together with the master application.

Include the notarized application, a deed or Property Appraiser printout, the plans and the executed Construction Cost Affidavit.

If a company owns the property, include its articles of incorporation with the registered or authorized agents listed, plus a copy of valid identification for the agent who signed. For work in a condominium common area, the package checklist lists an association approval letter and gives windows, doors, shutters and balconies as examples. Share the scope with the association so the letter identifies the same work as the application.

Sources: [1] North Bay Village Building Department — apply, contact the clerk and schedule inspections (checked November 23, 2026); [2] Download the North Bay Village permit application; [3] North Bay Village permit package checklist

Which fee applies at filing?

Use the Master Fee Schedule linked by the Village Clerk. The schedule dated October 20, 2026 sets the nonrefundable upfront building permit application fee at $150.

The older package checklist still shows a $125 minimum per application. Use the checklist for assembling the documents and the newer schedule for pricing.

If the base permit fee exceeds $400, a nonrefundable plan review payment equal to one-third of the base fee is due at submittal.

The Village credits that payment toward the total at issuance. The schedule prices some work by area and some by length. Concrete slabs, driveways and paving are listed at $0.50 per square foot, while a seawall or cap is listed at $53 per linear foot. It also lists a 50% discount on base fees for impact windows and doors, shutters, roofs, generators, solar installations and living seawalls. Ask the clerk to identify the applicable base fee and any separate trade charges before paying.

Sources: [4] Village Clerk’s master fee schedule — Resolution 2026-073; [3] North Bay Village permit package checklist

When do the plans go to Miami-Dade?

North Bay Village sends new buildings, additions, remodeling and commercial roofing through Miami-Dade environmental review (DERM).

The Village also calls for county fire approval on commercial projects and directs applicants planning demolition, interior renovation or roofing to the county’s asbestos guidance.

For county Municipal Approval, have the Village application and process number ready.

Miami-Dade also asks for its own Application for Municipal Permit, a contact sheet and the plans. Submit through the county’s Goldkey portal. To read county review comments, look up the county M-number, then open that number under Applications. Keep the Village reference alongside the M-number so a question goes to the reviewer who has the file.

Sources: [1] North Bay Village Building Department — apply, contact the clerk and schedule inspections (checked November 23, 2026); [6] Miami-Dade County Municipal Approval; [5] Open Miami-Dade’s Goldkey portal for county applications and status

What should the drawings show?

For replacement windows in the Village’s High-Velocity Hurricane Zone, open the residential Windows/Doors checklist.

It calls for existing and proposed plans locating the openings, exterior elevations, a schedule identifying the frames and glass, photos of the windows being replaced, wind-load calculations and product approval information with installation specifications. Numbering the openings consistently lets a reviewer match a window on the floor plan to its entry in the schedule.

For a new, repaired or replaced driveway or walkway, the Village wants calculations showing how much of the front yard is covered and specifications showing how readily water passes through the proposed material.

On property directly adjoining the Village shoreline, land development code section 8.16 ties development or substantial redevelopment to the Village’s seawall design criteria. For a structure proposed to exceed three stories, Village Code section 151.19 requires off-duty police officers during construction from permit approval through the certificate of occupancy.

Sources: [9] North Bay Village plan review and inspection checklist by permit type; [16] FEMA report to the Florida Building Commission on the HVHZ; [1] North Bay Village Building Department — apply, contact the clerk and schedule inspections (checked November 23, 2026); [11] North Bay Village seawall standards ordinance

Which flood map applies on the islands?

Open the property lookup on the Village’s Flood Awareness page and search the project address.

The county identifies September 11, 2009 as the date of the currently effective flood insurance rate maps. FEMA’s final notice lists North Bay Village among the communities whose revised maps take effect February 19, 2027. If the design or filing will span that change, send the map panel and the proposed filing date to the local floodplain management team through the form linked from Flood Awareness. The Village entered FEMA’s Community Rating System at Class 8.

Sources: [10] North Bay Village Flood Awareness and property flood lookup; [12] Miami-Dade County current flood maps and CRS participation; [13] FEMA final flood hazard determinations for North Bay Village and other Miami-Dade communities; [17] North Bay Village Community Rating System program

How to request a Village inspection

Send the request to [email protected] and identify the permit, address, unit and trade.

Building inspections are available each weekday. Roofing is available Tuesday through Friday, and the regular electrical, mechanical and plumbing inspection days are Tuesday and Thursday. A crew coordinating a roof inspection with an electrical inspection can request a Tuesday or Thursday and confirm both appointments with the clerk.

The Village lists a different schedule for residential projects with more than 10 units and commercial projects with more than 200 occupants.

Inspections for those projects are available Monday through Friday during allowed work times. On the jobsite, the ordinary construction window runs from 8:00 am to 5:00 pm on weekdays, excluding observed holidays. The Building Department’s list of forms includes a Request for Extended Construction Hours.

Sources: [1] North Bay Village Building Department — apply, contact the clerk and schedule inspections (checked November 23, 2026)

Drawings for a North Bay Village submission

Pineland Engineering can prepare the opening schedule, structural calculations and installation details for a Village window application.

For a driveway, Pineland can use the survey and proposed paving dimensions to prepare a site plan and front-yard coverage calculation. Sending the designer the selected window approval or paving specification gives the drawings and the clerk’s supporting documents a common reference.

Sources: [9] North Bay Village plan review and inspection checklist by permit type; [1] North Bay Village Building Department — apply, contact the clerk and schedule inspections (checked November 23, 2026)

What Do People Ask About North Bay Village Building Department?

How can I search for a North Bay Village permit by address?

Open Permits and Inspections Reports on the Building Department page. For example, the FY 24 Permits Issued Report lists the main address, parcel, permit number, issue date and status. Search the PDF for the street or parcel, then use the permit number on the Village Clerk’s Public Records form to request the permit or its final inspection record. For a pending Village application, ask the Building Clerk for its current status.

Can a North Bay Village condo owner file as an owner-builder?

The Village checklist limits the owner-builder application to the owner’s primary residence and excludes condominium units. For an eligible home, the owner submits the Owner-Builder Affidavit with the permit application. A condo owner replacing common-area windows should review the association letter and window documents with the contractor.

Do I need a permit for a shed in North Bay Village?

The Village application has a Shed permit type. The fee schedule lists $150 for a new prefabricated metal or wood storage shed or utility building, plus any applicable mechanical, electrical or plumbing charges. Give the clerk the shed dimensions, material and proposed location to confirm what to file for that property.

How long does North Bay Village plan review take?

For a roofing permit under $15,000 on an existing single-family home, Florida Statutes section 553.792 gives the Village five business days to approve, approve with conditions or deny a complete and sufficient application when a Village plans reviewer handles it, unless the applicant waives the timeframe in writing. For a different scope, give the Building Clerk the work description and Village reference to check current timing. For a commercial roof, also check county comments under the M-number.

Which Florida Building Code applies to a year-end Village application?

For a Village filing in November, the Florida Building Code 8th Edition (2023) applies. It went into effect December 31, 2023. The transition to the 9th Edition (2026) takes effect December 31, 2026. If the project also needs Miami-Dade approval, the county portal says submissions after 4 pm on December 30, 2026 must meet the new edition. Check the Village email intake cutoff separately with the Building Clerk.