Bay Harbor Islands Building Department

Pineland Engineering prepares permit-ready construction documents for Bay Harbor Islands, Miami-Dade County, Florida projects and coordinates directly with the Bay Harbor Islands Building Department during plan review — so you get your permit faster.

Quick Answer

The Town of Bay Harbor Islands Building & Zoning Department handles building permits at 1045 95th Street, Trailer 3, Bay Harbor Islands, FL 33154. Call 305-993-1786 or visit Monday through Friday, 8 a.m. to 4 p.m. For online filing, use the department’s GovWell link below.

For construction inside Bay Harbor Islands, start with the Town’s Building & Zoning office. Its department page links to GovWell for permits and has the fillable application, zoning map and Design Review Board package under Related Documents. The Town’s separate construction instructions still describe Citizenserve. If you already have an application there, call the permit counter with its number before opening a second file.

Where Can I Verify the Official Requirements?

What to put in the Bay Harbor Islands permit application

Start with the fillable form on the department page. Enter the job address and property folio.

For a trade application tied to an existing master permit, have that number ready for the field next to the folio. The project section asks for a specific work description, the value of all the work and the square footage. For condo windows, identify the openings on the floor plan and match them to the window specifications.

Check who will sign before you upload the form. It has separate notarized signature lines for the owner or authorized agent and for the contractor’s qualifier.

For condominium work, the Town lists an authorization letter from the association or management and reminds owners to obtain any applicable association approval before work starts.

For work involving multiple trades, the Town’s checklist calls for subcontractor applications with license and insurance documents alongside the master application.

Its contractor registration page lists no registration fee and directs insurers to email certificates directly with a cover letter describing the covered trades. Arrange the insurer’s email before uploading the trade application.

Sources: [1] Town Building & Zoning office, hours and forms (checked November 23, 2026); [3] Download the Town building permit application; [8] Town supporting-document checklist; [9] Town contractor registration and insurance instructions

When windows, driveways or additions change the exterior

Bay Harbor Islands requires approval from the Town Planner, the Design Review Board or both for exterior changes.

That includes paint, windows, doors, signs, awnings, fences, driveways and additions. Before choosing materials, show the planner what is there now and what you want to change. For a window, a photo of the existing opening and the proposed product sheet let staff see the difference. For a driveway, a site plan can show whether the work reaches the public sidewalk.

If the project goes to the board, Town staff must approve the submission before it can go on the agenda.

For internal review, the board checklist asks for two 24-by-36-inch plan sets. Once staff clears the package, deliver two sets at that size, five 11-by-17-inch sets and the combined files on a USB drive. The deadline is 10 days before the meeting, or 20 days if public notice is required. Confirm the actual meeting date with the planner before arranging printing.

Sources: [7] Town construction permit and exterior approval instructions; [5] Design Review Board fees, checklist and agenda deadlines

Which fees apply to the work?

The building fee schedule linked by the department is Resolution 2555.

Its new-construction line lists 3% of job cost with a $150 minimum. An addition or alteration to an existing structure has a separate line at 2% with the same $150 minimum. Both lines call for a copy of the contract. The schedule also lists an upfront, nonrefundable processing fee for residential and commercial permits. Ask for an itemized amount before paying, especially if the job includes trade permits.

Design review has its own charges. The board’s application package lists $5,000 for a major new application.

Its minor, revision or addition line lists $2,500 for single-family projects and $4,000 for multifamily or commercial work. The checklist limits minor review to changes under 25%. Ask the planner how that limit applies to your drawings.

Sources: [1] Town Building & Zoning office, hours and forms (checked November 23, 2026); [4] Town building permit fee schedule · Resolution 2555; [5] Design Review Board fees, checklist and agenda deadlines

When the driveway work reaches a Town sidewalk

Work in a Bay Harbor Islands right-of-way, including a road or sidewalk, requires a right-of-way permit and a maintenance of traffic plan.

Public Works asks for the traffic plan over a color aerial map and lists state approvals for work on 96th Street (Kane Concourse). Email the completed right-of-way and traffic applications to [email protected].

Public Works says to allow up to 10 business days after staff receives all required documents.

Corrected submissions start a new review of up to five business days. Complex traffic plans can take longer. Ask Building & Zoning separately for the building permit review time.

Sources: [10] Public Works right-of-way permit and traffic plan

Flood maps and wind exposure for an island property

Ask Building & Zoning to read the Flood Insurance Rate Map for your address.

Staff can identify the base flood elevation, provide an existing FEMA Elevation Certificate and check the elevation for mechanical equipment. The Town’s ordinance cites the September 11, 2009 flood study and maps as amended. FEMA lists the Town under Miami-Dade County as Community Rating System Class 9 and names the Trailer 3 office as the local repository for the updated map effective February 19, 2027. If design and filing span that date, take the survey to the office to confirm which elevations to use.

For a remodel, ask the Town Floodplain Manager to compare your cost estimate with the structure’s market value before the improvement.

The Town’s floodplain guide classifies an improvement as substantial when its cost reaches or exceeds 49% of that value. The owner affidavit on the building application mentions 50% for federal flood criteria. Get the Town’s determination before using the affidavit percentage to budget the work. For development in a flood hazard area, the floodplain administrator can also require a separate approval under Town Code section 7½-4.

Bay Harbor Islands is in Miami-Dade’s High Velocity Hurricane Zone.

For replacement windows, take the product approval and specifications to exterior review so the planner can see the proposed model. For current Bay Harbor Islands permit applications, the Florida Building Code 8th Edition (2023) applies, effective December 31, 2023. Use the filing date when discussing plans for year-end work with the Town because the 9th Edition (2026) takes effect December 31, 2026.

Sources: [11] Town flood map and elevation certificate service; [13] Town flood damage prevention ordinance; [14] FEMA Community Status Book for Florida; [15] FEMA final flood map determination for Bay Harbor Islands; [12] Town floodplain guide for contractors and homeowners; [3] Download the Town building permit application; [16] Miami-Dade County product control and hurricane zone guidance; [8] Town supporting-document checklist; [17] Florida Building Commission code effective date; [18] Florida Building Commission report on the next code effective date

Schedule inspections and close out the permit

Call 305-993-1786 at least 24 hours ahead with the permit number, job address, inspection type and requested date. Give the name and phone number of the person arranging access.

Building inspections run Monday through Thursday from 10 a.m.

to 2 p.m. Electrical and plumbing share a Tuesday-through-Thursday morning window from 9 a.m. to noon. Mechanical runs on those same three days from 10 a.m. to 2 p.m. Schedule crews separately around Town Code section 12-26, which sets regular construction hours at 9 a.m. to 6 p.m. on weekdays, excluding holidays.

For closeout, use the department’s certificate of occupancy or completion application if either certificate applies to your job.

Have the master building permit number and folio handy. The form also has separate fields for the Miami-Dade municipal process and permit numbers.

Sources: [1] Town Building & Zoning office, hours and forms (checked November 23, 2026); [6] Town inspection requests and trade schedules; [19] Town certificate of occupancy or completion application

Drawings for Bay Harbor Islands design review

Pineland Engineering can prepare architectural and permit drawings for an addition going before the Town’s Design Review Board.

Its preliminary plan checklist calls for color views of all sides and a site plan showing the driveway, parking, walkways and setbacks. Bring the survey and the planner’s comments so we can show the same footprint on the board exhibits and the construction drawings. If the Town has an elevation certificate on file, send it with the survey for the flood design.

Sources: [5] Design Review Board fees, checklist and agenda deadlines; [11] Town flood map and elevation certificate service

What Do People Ask About Bay Harbor Islands Building Department?

Is Bay Harbor Islands served by the Bal Harbour Building Department?

Bay Harbor Islands has its own permitting office in Trailer 3 on 95th Street. For an address in Bal Harbour Village, use the Village Building Department.

How do I check an existing Bay Harbor Islands permit?

Use the account associated with your application. The Town’s Citizenserve instructions describe document uploads, card payments, inspection requests and results. If your file is missing in GovWell, call the counter with your Citizenserve permit number.

Does a small shed need a Bay Harbor Islands permit?

Ask Building & Zoning before buying the shed. Give staff the dimensions and a sketch showing the proposed location and distances to the lot lines. The department directs applicants to ask about exemptions for their specific work.

How long does Bay Harbor Islands design review take?

Ask whether the planner can approve the change or whether it needs a board hearing. Staff must clear the plans first. Then count back 10 days from the board meeting, or 20 days for public notices.

Can I schedule a plumbing inspection on a Monday?

The Town lists Tuesday, Wednesday and Thursday mornings for plumbing. Monday is on the building inspector’s schedule. Request plumbing at least 24 hours ahead and specify which morning you want.